8/26/2015 - Park Ridge Road Construction Updates

 

 

Updates as of 8/26/2015

Milling on Alberon, Stephen, Laurance and Catherine will commence on or about Thursday August 27th.  Paving will follow the week of September 1st.

 

Updates as of 8/17/2015

  

Ridge Avenue- Drainage is 100% complete. The ADA ramps are 80% complete. Curb pieces remain to be replaced. Topsoil/ seed restoration to follow.

Milling and paving to commence after water dept. is 100% complete with additional work.

 

2015 Road Improvements- Drainage is 98% complete and curbs 25% complete. Milling and paving on Alberon, Stephen, Catherine, Laurance- to commence week of 8/17. Work will be continuing on Third.

 

ADA Ramps on Park Ave- Work is proceeding on Park Avenue. Removal and replacement of deteriorated curbs along Veterans Memorial Park to follow. Anicitpated completion date by 8/21, weather permitting.


 

Updates as of 8/10/2015

 

Ridge Avenue- Drainage work complete.  Upon water utility work completion, replacement of 2 ADA ramps and curb work to follow.

  

Stephen Drive -Drainage & Concrete work on Stephen is complete. Upon water utility work completion, milling and paving to follow.

 

Third Ave- Drainage and curb work week of 8/10. Mill and pave to follow on or about week of 8/24.

 

Park Ave- ADA Ramp work to proceed week of 8/10 by NJ Transit ROW area.


Update AS OF 8/5/2015

Concrete work proceeding on Stephen/ Alberon this week.

Potential mill/ pave next week, week of 8/10 for that neighborhood.

Third Street

Drainage work proceeding, concrete work to follow by end of week and continue through week of 8/10. Potential, mill/pave  8/17.

Ridge Ave

Drainage work completed. Milling and paving will follow. 

ADA ramps- Park Ave- work to commence 8/10 and is scheduled to last one week, weather permitting.  

UPDATE AS OF 7/30/2015

2015 Road Improvement Project – DLS Contractor

Drainage work on Stephen Drive is complete. Contactor will begin Curb work on Monday. One curbing is complete Milling & Paving of Laurance, Stephen and Catherine will follow.

Drainage work has now begun on Third Street at Ridge Avenue intersection and will proceed south over the next 2 weeks or so. Once drainage work is complete, curbing will follow with milling and paving after that.

 

NJDOT Project – Ridge Avenue

Drainage work is continuing along Ridge Avenue, ADA ramp work begun on Ridge Avenue and will continue through the next week. Estimated milling and paving on Ridge Avenue mid-August.

Water department is working on repairs along Ridge Avenue also which may delay the milling and paving.

 

Park Avenue – ADA ramps and milling and paving

ADA ramp construction is scheduled to begin week of 8/3 weather permitting

Milling and Paving is scheduled to begin mid-August, weather permitting

 

Ridge Avenue Improvements

Drainage and curb work along with milling and paving will commence on, or about, July 20th on Ridge Avenue between 2nd Street and Pascack Road weather permitting.  The construction will occur between 7:30am and 5:00pm.  We'll make every effort possible to reduce any inconvenience.  We thank you for your patience.  

 

Click Here to View the Letter

  

Stephen Drive

Drainage, curb improvements and paving will begin on Stephen Drive on or about July 20th.  

 

Catherine Terrace & Laurance Court

Milling and paving will begin on or about July 20th.

 

Click Here to View the Letter

 

Park Avenue

Starting on or about the 7/27/15, Park Ridge in cooperation with Bergen County will commence ADA, curb, ramp and sidewalk improvements.  Upon completion the County will complete milling and paving.  Construction will be active from 7:30am-5pm

 